Tokyo venues hit by delays

By REUTERS
July 25, 2018

TOKYO: Construction delays at two key Olympic venues could force Tokyo Games organisers into a reshuffle of test event schedules, the organising committee said.

The Olympics Aquatics Centre, which will host swimming and diving events as well as the Sea Forest Waterway, venue for the rowing and canoeing events in 2020, were two months behind schedule, according to organisers. Both venues will be completed well before the Games’ opening ceremony on July 24, 2020, but organisers may have to shift test events to allow for the delays.

We have been informed that the two venues have a delay compared to the original schedule, said Tokyo 2020 spokesman Masa Takaya.

We are working closely with the Tokyo Metropolitan Government (TMG) and the respective federations to be able to sort out and possibly modify the test event schedule.

“Other than that, the schedules on the permanent venues are absolutely right on track.”

On Tuesday, Tokyo 2020 organisers released a progress report that said the Aquatics Centre would not be finished until Feb. 2020, the latest of any of the new permanent venues.

The Sea Forest Waterway will be pushed back to May, 2019, when it had previously been earmarked for completion by March.

With the first test events planned for mid-2019, organisers are hopeful the majority of venues will be ready to host many of the international federations and athletes that will descend on the Japanese capital in 2020. The TMG, the sports federation and Tokyo 2020 are under discussions to make sure the test events to be delivered in time, added Takaya.

Another challenge facing Tokyo 2020 organisers is responding to questions from some international federations — including sailing and baseball about Japan’s ability to deliver their events to Olympic standard.