close
Wednesday October 16, 2024

Nepra fines Fesco Rs10m over safety violation

Failure to meet these deadlines may result in additional penalties

By Our Correspondent
September 13, 2024

The National Electric Power Regulatory Authority (Nepra) headquarters can be seen. — Facebook/NEPRA/file
The National Electric Power Regulatory Authority (Nepra) headquarters can be seen. — Facebook/NEPRA/file

ISLAMABAD: The National Electric Power Regulatory Authority (Nepra) has imposed a fine of Rs10 million on the Faisalabad Electric Supply Company (Fesco) for failing to fully implement earthing and grounding of its high-tension (HT) and low-tension (LT) poles and structures in its service territory.

The power regulator also directed Fesco to complete earthing of all remaining steel structures within three months and of all PCC poles within one year. Failure to meet these deadlines may result in additional penalties.

The fine was levied after Nepra reviewed submissions made by Fesco during a hearing and determined that the company had not provided a satisfactory response to a show-cause notice issued earlier, according to an order released on Thursday.

“The Authority hereby decides to impose a fine amounting to Rs10,000,000 on the Licensee due to its failure pertaining to 100 percent execution of earthing/grounding of its HT/LT poles/structures in its service territory,” the order stated.

The company must pay the fine within 15 days and submit proof of payment to the Nepra. If Fesco fails to comply, Nepra warned it may recover the amount as arrears of land revenue or pursue other legal actions.

During a hearing on May 13, 2024, Fesco’s CEO reported that 46 percent of the earthing and grounding had been completed, with 60 percent expected by June 2024 and the remaining 40 percent by September 2024. Fesco requested an extension due to challenges such as deep boring requirements for proper grounding and delays caused by factors including budget constraints, bad weather and contractor shortages.

However, Nepra rejected these explanations, citing the slow pace of progress and the company’s responsibility to address safety hazards. The regulator pointed to several fatalities in recent years linked to safety issues, including the deaths of employees and members of the public.

Nepra emphasized that Fesco’s request for further meetings on the earthing of PCC poles appeared to be a delaying tactic, as procedures had already been communicated by the National Transmission and Dispatch Company (NTDC).