Sindh to set up 104MW gas-run power projects
KARACHI: Sindh government will set up two gas-run power projects with a cumulative generation capacity of 104.20 megawatts at Nooriabad industrial area under the public-private partnership mode, officials said on Wednesday. The officials said the National Electric Power Regulatory Authority (NEPRA) has already granted licences to two
By Javed Mirza
July 30, 2015
KARACHI: Sindh government will set up two gas-run power projects with a cumulative generation capacity of 104.20 megawatts at Nooriabad industrial area under the public-private partnership mode, officials said on Wednesday.
The officials said the National Electric Power Regulatory Authority (NEPRA) has already granted licences to two specially established companies, Sindh Nooriabad Power Company (Pvt) Ltd and Sindh Nooriabad Power Company Phase-II (Pvt) Ltd, for generating 52.10MW each.
“These will be the first-ever power projects to be executed by a province under the public-private partnership mode,” an official said.
The official said the government will soon apply for the tariffs to NEPRA. Total cost of the projects will be determined once the tariffs are approved, he added.
He said the provincial government has initiated gas supply agreement with the Sui Southern Gas Company for supplying of 10 million metric cubic feet/day of gas to each power project for 25 years.
K-Electric Limited will be the power purchaser of the upcoming projects as Hyderabad Electric Supply Company (HESCO) has expressed reluctance to purchase power from the Sindh government.
National Transmission and Despatch Company (NTDC) has also expressed its lack of interest in wheeling electricity from Sindh Nooribad power projects.
The official said the authority directed HESCO not to decline buying the electric power offered from any prospective investor without a legal reason.
He added that it also asked NTDC to adhere to the terms and conditions of its licence and not to deny any generation company of its rights to use its system for evacuating electricity.
According to an official document, Sindh government agreed to provide around Rs6.0 billion bank guarantees and cash margin of Rs600 million to the NBP for opening of letters of credit for the procurement of machinery and equipment for the power projects.
The officials said Sindh Bank will repay Rs2.805 billion of debts acquired for the projects in case of default by the project operators.
However, they said the provincial government will stop extending financial support once the power projects achieve the financial close.
The power sector is experiencing huge demand and supply gap. The government is making efforts to reduce this gap through exploiting indigenous resources.
The official said since the country’s law permits provinces to set up power generation facilities of any size, at any location and on fuel of their choice the Sindh government has decided to build, own and operate generation facilities at various industrial estates across the province.
The officials said the National Electric Power Regulatory Authority (NEPRA) has already granted licences to two specially established companies, Sindh Nooriabad Power Company (Pvt) Ltd and Sindh Nooriabad Power Company Phase-II (Pvt) Ltd, for generating 52.10MW each.
“These will be the first-ever power projects to be executed by a province under the public-private partnership mode,” an official said.
The official said the government will soon apply for the tariffs to NEPRA. Total cost of the projects will be determined once the tariffs are approved, he added.
He said the provincial government has initiated gas supply agreement with the Sui Southern Gas Company for supplying of 10 million metric cubic feet/day of gas to each power project for 25 years.
K-Electric Limited will be the power purchaser of the upcoming projects as Hyderabad Electric Supply Company (HESCO) has expressed reluctance to purchase power from the Sindh government.
National Transmission and Despatch Company (NTDC) has also expressed its lack of interest in wheeling electricity from Sindh Nooribad power projects.
The official said the authority directed HESCO not to decline buying the electric power offered from any prospective investor without a legal reason.
He added that it also asked NTDC to adhere to the terms and conditions of its licence and not to deny any generation company of its rights to use its system for evacuating electricity.
According to an official document, Sindh government agreed to provide around Rs6.0 billion bank guarantees and cash margin of Rs600 million to the NBP for opening of letters of credit for the procurement of machinery and equipment for the power projects.
The officials said Sindh Bank will repay Rs2.805 billion of debts acquired for the projects in case of default by the project operators.
However, they said the provincial government will stop extending financial support once the power projects achieve the financial close.
The power sector is experiencing huge demand and supply gap. The government is making efforts to reduce this gap through exploiting indigenous resources.
The official said since the country’s law permits provinces to set up power generation facilities of any size, at any location and on fuel of their choice the Sindh government has decided to build, own and operate generation facilities at various industrial estates across the province.
-
Northern Lights: Calm Conditions Persist Amid Low Space Weather Activity -
'Look What Andrew Has Done': Meghan Markle Defended On Jeremy Vine Show -
Apple, Google Agree To Make 'app Store' Changes Over UK Regulator Concerns -
Autodesk Files Lawsuit Against Google Over AI Video Tool Trademark Dispute -
San Francisco 49ers Player Shot Near Post-Super Bowl Party -
Kardashian-Jenner Clan Brings Lewis Hamilton Into The Fold: Watch -
Meghan Markle 'quietly Dreaded' As Ex-best Friend Receives Lucrative Offer For Bombshell Memoir About Duchess -
Blake Shelton, Gwen Stefani Make Big Move To Save Their Marriage -
Google Warns Of State-sponsored Cyberattacks Targeting Defense Sector Employees -
Ransom Deadline Passes: FBI Confirms ‘communication Blackout’ In Nancy Guthrie Abduction -
Jeff Bezos Hints At Blue Origin Moon Plans As Elon Musk Responds With Cautious Praise -
Zach Bryan Slams Turning Point USA Alternative Halftime Show: 'Embarrassing As Hell' -
South Korea Blames Coupang Data Breach On 'management Failures,' Not Cyber Attack -
‘Disgraced’ Andrew More Concerned About ‘issue Of His Legacy’ Than Epstein Links -
Instagram Plans New Snapchat-style App ‘Instants’ Amid Rising AR Competition -
Safer Internet Day 2026: Is Social Media Ban The Only Way To Protect Kids?