Hubco plans rise in coal project’s stake
KARACHI: Hub Power Company Limited (Hubco) is mulling to almost double its stake in an estimated two billion dollars of imported coal-run power project, touted as the biggest one in the China-Pakistan Economic Corridor (CPEC) initiative.
“Hubco now intends to increase its shareholding in China Power Hub Power Generation Company (Pvt) Limited (CPHGC), through its wholly-owned subsidiary Hub Power Holdings Limited from 26 percent to 47.5 percent,” Hubco said in a statement on Thursday to the Pakistan Stock Exchange.
“The increase in shareholding will be subject to corporate and regulatory approvals in China and Pakistan.”
CPHGC is a joint-venture between Hubco and China Power International Pakistan Investment Limited to set up two 660 megawatts of imported coal-based power plants in Hub, Balochistan. The latter currently holds majority 74 percent shareholding in the power project that also envisaged a dedicated coal jetty. Both the companies have agreed the valuation.
In January, CPHGC achieved the financial close for its two billion dollars worth of coal power project with 1,320 megawatts of production capacity and a jetty.
CPHGC is one of the largest CPEC projects estimated at more than $50 billion.
Located in Hub, Balochistan – 45 kilometres northwest of Karachi, the power project will provide nine billion kilowatt-hours of electricity to the energy grid every year during commercial operations, which will meet the electricity needs of four million households in Pakistan. The coal power project is expected to start operation in August 2019.
Two months back, the project achieved a major milestone by interconnecting with the national grid, subsequently achieving back energisation of its 500 kilovolts (kv) gas insulated switchgear from Jamshoro side of the transmission lines. With this achievement, the CPHGC officially entered into hot commissioning phase of the complex that would lead to synchronisation of its first unit with the national grid in December.
The process of power back-feeding was completed after a series of key steps such as line connection, site acceptance tests, high pressure test of gas insulated switchgear, injection test and inter-tripping test all witnessed by relevant regulatory authorities.
After energising the 500kv system, the CPHGC achieved energisation of start-up transformer and 10kv auxiliary power system, and preparing for the system commissioning of unit 1.
The milestone was achieved in collaboration with the production and technology departments of CPHGC and National Transmission and Dispatch Company.
-
Jennifer Aniston Already Decided Her Wedding Dress? -
Prince Harry, Meghan’s Hollywood Party Drama Exposes Chaotic PR Strategy -
Jennifer Garner Reacts To Savannah Guthrie's Video As Search For Nancy Guthrie Continues -
Bad Bunny Leaves Fans Worried With Major Move After Super Bowl Halftime Show -
Captain Jason Talks Personal Hardships He Faced Ahead Of 'Below Deck' Season 4 -
Anti-monarchy Group Reacts To Prince William, Kate Middleton Statement On Epstein Scandal -
Andrew 'must' Apologize Not Wider Royal Family For Jeffrey Epstein Links -
Super Bowl 2026: Why Didn't Epstein Survivors Ad Air On TV? -
'Harry Potter' TV Series Exec Teases 'biggest Event In Streaming': Deets -
Camila Mendes Finally Reveals Wedding Plans With Fiancé Rudy Mancuso -
Beatrice, Eugenie Blindsided By Extent Of Sarah Ferguson’s Epstein Links -
Girl And Grandfather Attacked In Knife Assault Outside Los Angeles Home -
Super Bowl Halftime Show 2026: What Did Trump Say About Bad Bunny? -
Piers Morgan Defends Bad Bunny's Super Bowl Performance, Disagrees With Trump Remarks -
Andrew Lands In New Trouble Days After Royal Lodge Eviction -
Instagram, YouTube Addiction Case Trial Kicks Off In California