PHC stops KP govt from awarding contracts directly to NLC, FWO
PESHAWAR: The Peshawar High Court on Thursday stopped the Khyber Pakhtunkhwa government from issuing work order of major construction projects to the National Logistics Cell and Frontier Works Organization till the next order of the court.
A division bench comprising Justice Waqar Ahmad Seth and Justice Younas Thaheem issued the restraining order in a writ petition filed by the Private Contractors Association, Khyber Pakhtunkhwa, in which it had challenged the award of the contract of mega projects to the two government construction companies.
During the hearing, the petitioners’ lawyer submitted that the provincial government on February 27 awarded contract of five mega projects to National Logistics Cell (NLC). These included Flyover at Warsak Road-Ring Road intersection, Level-II flyover at GT Road at the Ring Road intersection (Pir Zakori Flyover) in Peshawar, internal road rehabilitation projects in Peshawar city, Peshawar uplift programme and flyovers at the Jawad Chowk and Katlang Chowk in Mardan through direct contracting.
The lawyer for the private contractors submitted that the provincial assembly had enacted the Khyber Pakhtunkhwa Public Procurement Regulatory Authority (KPPRA) Act, 2012 to provide for the legal and regulatory framework for public procurement and promote transparency and accountability in the bidding for the projects.
However, he submitted that the provincial government then adopted KP Public Procurement of Goods, Works and Service Rules 2014. He said the rule 3(2) of the KPPRA Rules provided that deviation from normal methods of advertisement and response may be allowed in case of emergency or disaster. He said that insertion of Rule 3(2) (c) of the KPPRA Rules to directly award contract is illegal, unfair, discriminatory and against the KPPRA Act and it should thus be declared as void.
The private contractors claimed that Rule 3(2) (C) of the KPPRA Rules was unconstitutional and they were being discriminated by the government to award direct contracts to FWO and NLC without fair process of bidding.
As interim relief, the contractors prayed the court that any direct contracting/sourcing to government organizations over private sector entities under Rule 3(2) (c) of the KPPRA Rules may be stayed and the respondents may be restrained from awarding contract and work order to FWO and NLC pursuant to the impugned meeting on February 27, 2017 till the final decision of the petition.
-
Eric Dane’s Friends Initiate GoFundMe To 'support' His Two Daughters After His Death At 53 -
Internet Erupts After Candace Owens Claims Elon Musk And Sam Altman Are ‘not Human’ -
Will Princess Beatrice, Eugenie Stay In Contact With Andrew? Source Speaks Out -
‘AI Revolution Is Coming Fast & US Has No Clue,’ Bernie Sanders Warns Of Speed Of Disruption -
Hong Kong Touts Stability,unique Trade Advantages As Trump’s Global Tariff Sparks Market Volatility -
‘Miracle On Ice’ Redux? US Men Chase First Olympic Hockey Gold In 46 Years Against Canada -
Friedrich Merz Heads To China For High Stakes Talks In An Effort To Reset Strained Trade Relations -
Astronauts Face Life Threatening Risk On Boeing Starliner, NASA Says -
Hailey Bieber Reveals How Having Ovarian Cysts Is 'never Fun' -
Kayla Nicole Looks Back On Travis Kelce Split, Calls It ‘right Person, Wrong Time’ -
Prince William And Kate Middleton Extend Support Message After Curling Team Reaches Olympic Gold Final -
Nvidia CEO Praises Elon Musk, Calls Him An ‘extraordinary Engineer' -
Shia LaBeouf's Mugshot Released After Mardi Gras Arrest On Battery Allegations In New Orleans -
Timothee Chalamet Felt '17 Again' After Reunion With 'Interstellar' Director Christopher Nolan -
Conan O'Brien Speaks First Time After Rob Reiner's Killing -
Giant Tortoise Reintroduced To Island After Almost 200 Years