The repair of an 84-inch main water line on University Road is nearing completion and work is expected to complete within the next 14 hours, said a spokesperson for the Karachi Water & Sewerage Corporation (KWSC) on Sunday.
Once repairs are finalised, the water supply from the Dhabeji Pumping Station will resume.
The spokesperson stated that the repair work continued uninterrupted for 24 hours a day under the supervision of Chief Engineer WTM Zafar Palijo. A team of over 300 labourers, working in three shifts, along with Superintendent Engineers Tanveer Sheikh, Abdul Aziz and Muhammad Siddique Tanyu participated in the effort. Heavy machinery was also deployed at the site to facilitate the process.
The spokesperson explained that one significant cause of the delay was the extensive de-silting of the pipeline. During road construction, drilling machines used to build large pillars punctured the water line in two places, creating 16-foot-long holes. To prevent water pressure from leaking, debris, stones, and concrete were stuffed into these holes, resulting in 96 feet of accumulated concrete across six pipe sections.
This picture taken on January 30, 2023, shows commuters passing through the Empress Market in Pakistan's port city of...
The MOU signing ceremony between Fauji Fertilizer Company Limited and Adamjee Insurance Company Limited on January...
In this image, students arrive at their school on January 24, 2025. — OnlineThe Sindh government has announced...
Sindh Excise and Taxation Minister Mukesh Kumar Chawla chairs a meeting on January 24, 2025. — Screengrab via...
The meeting of the Grand Democratic Alliance regarding 2024 polls on January 24, 2025. — Screengrab via...
Representational image show a rescue worker waves to make way for an ambulance. — Reuters/FileAnother citizen lost...