Fuel loading for 1,100MW KANUPP-2 starts
ISLAMABAD: The fuel loading for newly built 1100 megawatt Karachi Nuclear Power Plant (KANUPP) Unit-2 kick-started on Tuesday after seeking permission from Pakistan Nuclear Regulatory Authority (PNRA).
After fuel loading, different tests will be started to ensure safety and standards compliance on International Atomic Energy Agency (IAEA) till March 2021 and then its operation will begin and its produced electricity will be connected to national grid. The per unit cost of electricity at Chashma Nuclear Power Plants stood at Rs11.16 and the cost of KANUPP Unit-2 will be hovering around Rs14 to Rs15 per unit, keeping in view estimated cost of newly constructed nuclear power plants. The K-3 project is expected to be completed after 10 months of completion of K-2.
The construction of two nuclear power plants, K-2 and K-3 based on Chinese ACP1000 concept started in August 2015 and May 2016, close to the KANUPP site in the outskirts of Karachi city. ACP1000 is a state-of-the-art, 1100MW, Gen-III design based on PWR. The units are scheduled to come online in 2020 and 2021. Both K-2 and K-3 are also under IAEA safeguard since March 2017.
According to Pakistan Atomic Energy Commission (PAEC) announcement, fuel loading for the newly built, 1100MW, Karachi Nuclear Power Plant Unit-2 (K-2) started on Tuesday, after obtaining fuel load permit from Pakistan Nuclear Regulatory Authority (PNRA). This was announced by the spokesperson of PAEC. The fuel loading was witnessed by DG SPD Lt. Gen. Nadeem Zaki Manj, PAEC Chairman Muhammad Naeem, Member Power PAEC along with Chinese dignitaries and officials.
K-2 is 1100MW Pressurised Water Reactor (PWR) based on the Chinese HPR-1000 technology, which is 3rd Generation Plant equipped with advanced safety features. The construction of K-2 Plant started on August 31, 2015 and its commercial operation will begin in April 2021, after undergoing several operational and safety tests. K-2 is one of the two 1100MW nuclear power plants being constructed at Karachi. The other plant, K-3 is expected to become operational by the end of 2021.
The completion of these nuclear power plants has remained largely on schedule, despite the difficult times due to COVID-19 pandemic, the statement concluded.
-
Why Prince William Releases Statement On Epstein Scandal Amid Most 'challenging' Diplomatic Trip? -
Historic Mental Health Facility Closes Its Doors -
Top 5 Easy Hair Fall Remedies For The Winter -
Japan Elections: Stock Surges Record High As PM Sanae Takaichi Secures Historic Victory -
Prince William, Kate Middleton Finally Address Epstein Scandal For First Time: 'Deeply Concerned' -
Kim Kardashian Promised THIS To Lewis Hamilton At The 2026 Super Bowl? -
Andrew Mountbatten-Windsor Throws King Charles A Diplomatic Crisis -
Barack Obama Hails Seahawks Super Bowl Win, Calls Defense ‘special’ -
Pregnant Women With Depression Likely To Have Kids With Autism -
$44B Sent By Mistake: South Korea Demands Tougher Crypto Regulations -
Lady Gaga Makes Surprising Cameo During Bad Bunny's Super Bowl Performance -
Paul Brothers Clash Over Bad Bunny's Super Bowl Performance -
South Korea: Two Killed As Military Helicopter Crashes During Training -
Elon Musk Unveils SpaceX’s Moon-first Strategy With ‘self Growing Lunar City’ -
Donald Trump Slams Bad Bunny's Super Bowl Performance: 'Absolutely Terrible' -
Jake Paul Criticizes Bad Bunny's Super Bowl LX Halftime Show: 'Fake American'