Neelum-Jhelum power project: CoD of unit-4 to be attained in Dec
ISLAMABAD: The Commercial Operation Date (CoD) of Rs503 billion Neelum-Jhelum hydropower project will now complete in December this year, as the fourth unit of 242.25MW has been dismantled again.
The existing parts of the unit are being replaced and this process will be completed by mid of November. Chinese experts from Harbin city are installing new spare parts. The rotor of the unit got damaged at the very outset of making the project operational.
The unit-4 stopped functioning when the rubber ring of turbine got leaked. The unit-4 was then repaired and made operational, but the top management of the project refused to extend to the contractor the taking over certificate (ToC) unless genuine parts were replaced.
Chief Executive Officer of Neelum- Jhelum Hydropower Company Limited (NJHPCL) Brig (Retd) Mohammad Zareen said: “Yes, unit-4 has been dismantled and the required spare parts are being replaced by the Chinese team that came from Herbin city of China.
He said the process will take more than a week and after that the unit will start operating. He said the same unit 4 had already completed its reliability period. “And more importantly, the CoD of unity-4 will also be attained in December.”
The project, Mr Zareen said, has 4 units with each having the capacity to generate 242.25MW out of which the management has achieved the CoDs of three units. Once the CoD of the whole project is achieved, the government will withdraw the Neelum-Jhelum surcharge of Re0.10 per unit being charged from the end consumers in the electricity bills.
Mr Zareen said so far the project had generated 1.8 billion electricity units. To a question, he said 280 cumecs water is needed to run the four turbines to generate 969 MW of the project. The water flow has now dwindled in Neelum river to 90 cumecs and in the month of January the water flows will further go down to 36 cumecs. The water flows start improving from February and till April they will increase to 280 cumecs and from April to August, the project will be in a position to generate 969MW power for five months a year.
In the remaining months, water is stored in the dam and during peak demand hours the project generates the maximum electricity. The Executive Committee of National Economic Council (Ecnec) in 2002 approved the project at the cost of Rs84.502 billion.
-
Prince Harry Receives Praises For Exposing Dark Side Of British Tabloids -
Andrew Forces Beatrice, Eugenie To Lose $60 Million Safety Net Saved For Retirement -
Nvidia CEO Jensen Huang To Visit China To Push Re-entry Into AI Chip Market -
U.S. On Verge Of Losing Measles-free Title Due To Outbreak -
Harry Styles Excites Fans As He Announces Release Date Of New Song -
Japan’s Ex-PM Shinzo Abe’s Killer Is Set To Be Sentenced: How Much Punishment Could He Face? -
Prince Harry, Meghan Markle’s Return To UK Could Create Royal Family Dilemma -
Prince Harry Turns Troubled With No Sense Of Home: ‘Isolation Is Getting To Him Mentally’ -
Vitamin D Link To Respiratory Diseases Will Shock You -
A$AP Rocky Gives His Take On Children's Budding Personalities -
Elijah Wood On Return To 'Lord Of The Rings' Universe -
Princess Beatrice, Eugenie Resort To Begging Sarah Ferguson: 'It'll Bring Disaster For The Whole Family' -
Jenny Slate Hails Blake Lively Amid Lawsuit Against Justin Baldoni -
Sophie Wessex Shares 'frustration' From Early Days In Royal Family -
Jason Momoa's Aquaman Unseen Snap Revealed -
Prince Harry Taught Only Way King Charles 'will Take Him Seriously'