Genco seeks tariff for 1320MW coal-fired plant
KARACHI: The Jamshoro Power Company Limited – Genco-I – has approached the National Electric Power Regulatory Authority (Nepra), seeking tariff determination for its $1.64 billion coal-fired power plant of 1,320MW to be set up in Jamshoro, a statement said on Monday.The project will be sponsored and executed by Genco Holding
By our correspondents
January 27, 2015
KARACHI: The Jamshoro Power Company Limited – Genco-I – has approached the National Electric Power Regulatory Authority (Nepra), seeking tariff determination for its $1.64 billion coal-fired power plant of 1,320MW to be set up in Jamshoro, a statement said on Monday.
The project will be sponsored and executed by Genco Holding Company Limited (GHCL), whereas the implementing agency Jamshoro Power Company Limited would also be responsible for operations and maintenance of the project.
These two units of 660MW each are expected to be the first of the new coal-fired power plants to be commissioned and will be able to contribute a gross generating capacity of 1,320MW, which is equivalent to 20 percent of the current electricity shortfall, at an approximate fuel cost of 20 percent and 30 percent relative to costs of HSD and RFO, respectively.
The feasibility study for this project has been completed by US Power Consult LLC and the PC-I has also been compiled and approved by the Ecnec.
Some 30 percent of the project will be financed through equity injected by the government of Pakistan through Genco I, whereas the remaining amount is to be secured through debt financing, it said.
To this effect, a significant portion of the required debt financing had already been arranged through a mix of financing facilities from the Asian Development Bank (ADB) and the Islamic Development Bank (IDB), whereas the remaining amount will be arranged through commercial debt arrangements.
The project has been estimated to be established at a total cost of $1.637 billion. On a gross per megawatt basis, the cost is equal to $1.241 million per MW.
As a condition precedent for the financing arrangements of the ADB and IDB, the project tariff needs to be awarded before initiating the process for EPC contracting, it said.
The project will initially utilise imported sub-bituminous coal till such time that extraction of lignite from Thar commences and is available for commercial use.
The project has an estimated construction time of 48 months, subsequent to commencement of construction. The estimated life of the project is 30 years, it added.
The project will be sponsored and executed by Genco Holding Company Limited (GHCL), whereas the implementing agency Jamshoro Power Company Limited would also be responsible for operations and maintenance of the project.
These two units of 660MW each are expected to be the first of the new coal-fired power plants to be commissioned and will be able to contribute a gross generating capacity of 1,320MW, which is equivalent to 20 percent of the current electricity shortfall, at an approximate fuel cost of 20 percent and 30 percent relative to costs of HSD and RFO, respectively.
The feasibility study for this project has been completed by US Power Consult LLC and the PC-I has also been compiled and approved by the Ecnec.
Some 30 percent of the project will be financed through equity injected by the government of Pakistan through Genco I, whereas the remaining amount is to be secured through debt financing, it said.
To this effect, a significant portion of the required debt financing had already been arranged through a mix of financing facilities from the Asian Development Bank (ADB) and the Islamic Development Bank (IDB), whereas the remaining amount will be arranged through commercial debt arrangements.
The project has been estimated to be established at a total cost of $1.637 billion. On a gross per megawatt basis, the cost is equal to $1.241 million per MW.
As a condition precedent for the financing arrangements of the ADB and IDB, the project tariff needs to be awarded before initiating the process for EPC contracting, it said.
The project will initially utilise imported sub-bituminous coal till such time that extraction of lignite from Thar commences and is available for commercial use.
The project has an estimated construction time of 48 months, subsequent to commencement of construction. The estimated life of the project is 30 years, it added.
-
Why Prince William Releases Statement On Epstein Scandal Amid Most 'challenging' Diplomatic Trip? -
Historic Mental Health Facility Closes Its Doors -
Top 5 Easy Hair Fall Remedies For The Winter -
Japan Elections: Stock Surges Record High As PM Sanae Takaichi Secures Historic Victory -
Prince William, Kate Middleton Finally Address Epstein Scandal For First Time: 'Deeply Concerned' -
Kim Kardashian Promised THIS To Lewis Hamilton At The 2026 Super Bowl? -
Andrew Mountbatten-Windsor Throws King Charles A Diplomatic Crisis -
Barack Obama Hails Seahawks Super Bowl Win, Calls Defense ‘special’ -
Pregnant Women With Depression Likely To Have Kids With Autism -
$44B Sent By Mistake: South Korea Demands Tougher Crypto Regulations -
Lady Gaga Makes Surprising Cameo During Bad Bunny's Super Bowl Performance -
Paul Brothers Clash Over Bad Bunny's Super Bowl Performance -
South Korea: Two Killed As Military Helicopter Crashes During Training -
Elon Musk Unveils SpaceX’s Moon-first Strategy With ‘self Growing Lunar City’ -
Donald Trump Slams Bad Bunny's Super Bowl Performance: 'Absolutely Terrible' -
Jake Paul Criticizes Bad Bunny's Super Bowl LX Halftime Show: 'Fake American'