Swat Expressway being partially opened today
PESHAWAR: The Swat Expressway, a mega project of the Khyber Pakhtunkhwa (KP) government, is being opened partially for traffic today despite being incomplete.
Work on the 81-kilometre road from Karnal Sher Khan Interchange on Motorway M-I to Chakdara was launched in August 2016. The project was scheduled to be completed in December 2017.
However, it couldn’t be completed in time, but the Pakistan Tehreek-e-Insaf (PTI) government, for which Swat Expressway is an iconic project, wants to inaugurate the road despite being incomplete.
The 50-kilometre portion of the Swat Expressway from Karnal Sher Khan Interchange to Katlang would be inaugurated today as per the government’s announcement.
Since the government is going to complete its tenure on May 28, Chief Minister Pervez Khattak is in a hurry to inaugurate even the incomplete project.
He was scheduled to partially open the Bus Rapid Transit (BRT) project on Sunday, but couldn’t do so. The inauguration of the incomplete Swat Expressway is scheduled for today. The PTI government couldn’t complete both the mega projects it had launched.
Though opening of the expressway at this movement would serve no purpose as the main beneficiaries, the people of Malakand division cannot use it until completion of the remaining portion up to Chakdara.
As per government version, the Swat Expressway portion from Karnal Sher Interchange to Katlang will be opened. The remaining part up to Chakdara would be inaugurated in December.
Interestingly, the portion to be opened today also is not fully operational as bridges at many places have not been constructed.
Addressing the groundbreaking ceremony at the starting point (Karnal Sher Khan Interchange) on August 25, 2016, the chief minister had said the highway would be completed in 15 months.
“Though the stipulated time period for the project completion is 18 months, the FWO [Frontier Works Organisation] has assured its completion in 15 months. I am hopeful keeping in view its track record, the FWO would complete it before the stipulated time,” he had said.
Pervez Khattak during a visit to the project site said first section of the motorway from Karnal Sher Interchange to Katlang would be opened in March but that, too, was delayed till May.
The provincial government is paying Rs17 billion of the Rs40 billion to be spent on the project. The FWO would collect the remaining amount through toll tax in 25 years.
To make the Swat Expressway more beneficial, 10,000 acres of land has been acquired near Karnal Sher Interchange for establishment of an industrial zone under the China Pakistan Economic Corridor (CPEC).
The Swat Expressway is the first of its kind being executed by a provincial government. It will benefit Swabi, Mardan, Malakand, Swat, Shangla, Lower Dir, Upper Dir and Chitral districts and Bajaur Agency.
On completion, it would reduce the travel time from Chakdara to Peshawar or Islamabad at least by two hours.
The 81-kilometre long and 80-meter wide expressway will have two tunnels of three kilometres and interchanges at Dhobian, Ismaila, Bakhshali, Katlang, Palai and Chakdara. Over 18,000 vehicles would ply it daily.
-
5 Celebrities You Didn't Know Have Experienced Depression -
Trump Considers Scaling Back Trade Levies On Steel, Aluminium In Response To Rising Costs -
Claude AI Shutdown Simulation Sparks Fresh AI Safety Concerns -
King Charles Vows Not To Let Andrew Scandal Overshadow His Special Project -
Spotify Says Its Best Engineers No Longer Write Code As AI Takes Over -
Michelle Yeoh Addresses 'Wicked For Good' Snub At 2026 Oscars -
Trump Revokes Legal Basis For US Climate Regulation, Curb Vehicle Emission Standards -
DOJ Blocks Trump Administration From Cutting $600M In Public Health Funds -
2026 Winter Olympics Men Figure Skating: Malinin Eyes Quadruple Axel, After Banned Backflip -
Meghan Markle Rallies Behind Brooklyn Beckham Amid Explosive Family Drama -
Scientists Find Strange Solar System That Breaks Planet Formation Rules -
Backstreet Boys Voice Desire To Headline 2027's Super Bowl Halftime Show -
OpenAI Accuses China’s DeepSeek Of Replicating US Models To Train Its AI -
Woman Calls Press ‘vultures’ Outside Nancy Guthrie’s Home After Tense Standoff -
Allison Holker Gets Engaged To Adam Edmunds After Two Years Of Dating -
Prince William Prioritises Monarchy’s Future Over Family Ties In Andrew Crisis