Work on Gulberg-Rawat section to begin next week
Islamabad : The construction work on the next phase of Islamabad Expressway Signal Free Corridor (Gulberg-Rawat) will start in the coming days to regulate traffic flow on one of the most traffic-laden artery, said a top official of the Capital Development Authority (CDA).
“All the relevant departments are mobilized, machinery is moving and the work will start with full force as alternate traffic plan is being prepared by member engineering, director traffic planning, and traffic police,” CDA Chairman Amer Ali Ahmed told this agency.
The work on the final phase of the Islamabad Expressway Signal Free Corridor has remained in limbo for the last couple of years, mainly due to financial constraints, faced by the civic agency, whereas it is the public who have been bearing the brunt of long-hour traffic clogs daily while traveling on such road.
Talking to this scribe, the project director said initially, the CDA would add two more lanes on both sides of one kilometre patch on Korang Bridge and construct an Underpass at the Public Works Department (PWD) intersection under the PC-I, approved by the Central Department Working Party with an estimated cost amounting Rs1.6 billion.
The timeline for widening Korang Bridge and PWD underpass had been set for 15 and seven months, respectively, he added.
The director said the contractors had been hired through a transparent bidding process for executing the project and it was expected that the construction work would be started by the next week.
When asked about the rest of the work on the project that involved the addition of two more lanes on both sides of the expressway till Rawat and the construction of three more bridges, he said the option of completing the project under Public Sector Development Programme (PSDP) plus was under consideration.
The PSDP plus was a concept of materializing a project under the Public-Private Partnership, he explained.
A senior official of Islamabad Traffic Police (ITP) said the expansion of Islamabad Expressway was much-imperative as some 420,000 vehicles were plying on this road daily.
The road had seventeen entries including Dhoke Kala Khan, Sohan, Kurri Road East and West, Gulberg, PWD, Bahria Town, Sihala, Kahuta Road, G-T Road Zia Masjid East and West, Lehtrar Road, KRL, Fazaiya Colony, Ghuari Town and others.
He said the expansion of the expressway should be completed at the earliest as more construction was also expected along the Islamabad Highway in coming days.
To a question, he said more than forty-two staffers of ITP were being deployed from Koral to Rawat for handling daily traffic load.
Besides, the entry of heavy traffic at the expressway had been banned during the office timings.
-
18-month Old On Life-saving Medication Returned To ICE Detention -
Cardi B Says THIS About Bad Bunny's Grammy Statement -
Major Hollywood Stars Descend On 2026 Super Bowl's Exclusive Party -
Sarah Ferguson's Silence A 'weakness Or Strategy' -
Garrett Morris Raves About His '2 Broke Girls' Co-star Jennifer Coolidge -
Winter Olympics 2026: When & Where To Watch The Iconic Ice Dance ? -
Melissa Joan Hart Reflects On Social Challenges As A Child Actor -
'Gossip Girl' Star Reveals Why She'll Never Return To Acting -
Chicago Child, 8, Dead After 'months Of Abuse, Starvation', Two Arrested -
Travis Kelce's True Feelings About Taylor Swift's Pal Ryan Reynolds Revealed -
Michael Keaton Recalls Working With Catherine O'Hara In 'Beetlejuice' -
King Charles, Princess Anne, Prince Edward Still Shield Andrew From Police -
Anthropic Targets OpenAI Ads With New Claude Homepage Messaging -
US Set To Block Chinese Software From Smart And Connected Cars -
Carmen Electra Says THIS Taught Her Romance -
Leonardo DiCaprio's Co-star Reflects On His Viral Moment At Golden Globes