Murad orders acquisition of land for M-6 by August 7
Sindh Chief Minister Syed Murad Ali Shah, while presiding over a meeting on Thursday to review progress and challenges in the M-6 Hyderabad-Sukkur Motorway project, noted that litigation had contributed to delays in the project and emphasised that all mutations of state and private land required for the M-6 project must be completed by August 7, 2025.
Officials said Shah focused on resolving land acquisition issues and accelerating construction efforts so that work could commence in the upcoming fiscal year. The meeting, which was held at the CM House, was attended by Chief Secretary Asif Haider Shah, SMBR Baqaiullah Anar, Principal Secretary to CM Agha Wasif, Hyderabad Commissioner Bilawal Memon, Finance Secretary Fayaz Jatoi and others.
According to the briefing by the chief secretary, a total of 7,226.32 acres of land is required for the motorway stretch from Jamshoro to Sukkur, of which 884.04 acres belong to the Sindh government, while 6,342.28 acres are privately owned.
Further instructions included the acquisition of 1,390.01 acres in Shaheed Benazirabad, 1,471.18 acres in Naushahro Feroze, 1,802.1 acres in Khairpur, and 26.36 acres in Sukkur by the August 7 deadline.
The CM announced that his government had allocated Rs4.5 billion for bridge financing, while the National Highway Authority (NHA) would provide Rs6.27 billion for the project. He directed the Hyderabad commissioner to report on the acquisition of 342.15 acres of private and government land and also instructed him to ensure that the land required in Matiari was acquired within two days. Further instructions included the acquisition of land in Shaheed Benazirabad, Naushehro Feroze, Khairpur and Sukkur before the deadline. The CM said he wanted to initiate work on the M-6 motorway promptly in the new fiscal year, underscoring the project's importance for economic development in Sindh. The National Highway Authority (NHA) chairman assured the CM that he would complete the entire tendering process and award the work by February 2026, allowing physical work to commence by March 2026.
-
Jay-Z And Beyoncé's Mansion Suffers Damage After Driver Crashes Through Gates -
Benny Blanco Admits To Unexpected Phobia As He Travels To See Selena Gomez: 'Things We Do For Love' -
Andrew Mountbatten-Windsor Hits Another Phase Of Rock Bottom -
Jelly Roll And Bunnie Xo Complete Divorce Proceedings Weeks After Filing -
Meghan Markle Planning UK Return? Here’s The Truth -
Princess Eugenie Turns Up Andrew’s Temper With ‘personal Insult’ Over New Baby -
Jennifer Lopez Reveals The Relationship Quality That Wins Her Over -
What Happened Inside Highgrove House Between King Charles & Prince Harry: Expert -
‘Outcast’ Prince Harry’s Friend Exposes What He Really Feels About The American Dream With Meghan -
Will Smith Named In New Court Filing Amid Jada Pinkett Smith Case -
Spice Girl Mel C Reportedly Planning Intimate Lake District Wedding -
More Than 100 Homes Destroyed As Massive Wildfire Sweeps Southern Norway -
Meghan Markle’s Emmy Nod Sends The Media Into A Frenzy: ‘Is It Even Credible Anymore?’ -
Dylan Sprouse Opens Up About Scary Late-night Break-in At Los Angeles Home -
Ariana Grande 'happy' With Ricky Alvarez After Surprise Concert Shoutout -
Meta, Anthropic Seek $10 Billion AI Compute Lease Deal: Report