PDA gives deadline for completion of Peshawar BRT
PESHAWAR: Finally the Peshawar Development Authority (PDA) has set a deadline for the completion of the remaining part of Bus Rapid Transit (BRT), Peshawar. The minor work on the main corridor and finishing works of three building projects at Hayatabad, Dabgari, and Chamkani is expected to be completed by the end of June 2022.
The PDA had already paid an amount of Rs 37.687 billion to the contractor for the civil work of the main corridor and three incomplete mega plazas. However, the BRT corridor is fully operational without any hindrance but three depots are still incomplete.
A controversy had arisen over the remaining work of Bus Rapid Transit in 2020. The JV Chinese and local contractors had refused to continue work on the BRT corridor and three mega shopping plazas (depots) worth Rs 10 billion. Construction work on all three depots had been stalled for months. The Peshawar Development Authority has decided to replace the JV contractors to complete the remaining work of the PTI flagship project. Asian Development Bank has approved the assignment agreement to hand over the remaining work to subcontractors.
According to data available with this correspondent, the BRT Reach-I, (Chamkani to Balahisar Fort) was 97.72% completed while 2.28% of work is in progress. The PDA has paid Rs 9,307,311,059.41 to the contractor and the remaining work will be completed by March 2022. A de-scoping agreement has been signed and work was awarded to the subcontractor.
Reach-II (Balahisar Fort to Aman Chowk ) 96.51 per cent of work has been completed, while only 3.49% minor work is awarded to a subcontractor to complete by March 2022. PDA has paid an amount of Rs 9,541,582,184.04 to the main contractor.
Similarly, 94.59% of the work of Reach-III (Aman Chowk to Karkhano Market) has been completed and 5.41% of work is awarded to a subcontractor and the completion date is March 2022. PDA has already paid an amount of Rs 12,740,980,829.95 to the main contractor. Three mega shopping and car plazas are also part of the BRT but the contractor had refused to complete the work on these plazas. The Hayatabad Depot, 81.33%, Chamkani 82.71, and Dabgari has76.24% per cent of work has been completed so far and 18.67%, 17.29, and 23.76% work is remaining, respectively.
-
Nick Jonas Gets Candid About His Type 1 Diabetes Diagnosis -
King Charles Sees Environmental Documentary As Defining Project Of His Reign -
James Van Der Beek Asked Fans To Pay Attention To THIS Symptom Before His Death -
Portugal Joins European Wave Of Social Media Bans For Under-16s -
Margaret Qualley Recalls Early Days Of Acting Career: 'I Was Scared' -
Sir Jackie Stewart’s Son Advocates For Dementia Patients -
Google Docs Rolls Out Gemini Powered Audio Summaries -
Breaking: 2 Dead Several Injured In South Carolina State University Shooting -
China Debuts World’s First AI-powered Earth Observation Satellite For Smart Cities -
Royal Family Desperate To Push Andrew As Far Away As Possible: Expert -
Cruz Beckham Releases New Romantic Track 'For Your Love' -
5 Celebrities You Didn't Know Have Experienced Depression -
Trump Considers Scaling Back Trade Levies On Steel, Aluminium In Response To Rising Costs -
Claude AI Shutdown Simulation Sparks Fresh AI Safety Concerns -
King Charles Vows Not To Let Andrew Scandal Overshadow His Special Project -
Spotify Says Its Best Engineers No Longer Write Code As AI Takes Over