PDA gives deadline for completion of Peshawar BRT
PESHAWAR: Finally the Peshawar Development Authority (PDA) has set a deadline for the completion of the remaining part of Bus Rapid Transit (BRT), Peshawar. The minor work on the main corridor and finishing works of three building projects at Hayatabad, Dabgari, and Chamkani is expected to be completed by the end of June 2022.
The PDA had already paid an amount of Rs 37.687 billion to the contractor for the civil work of the main corridor and three incomplete mega plazas. However, the BRT corridor is fully operational without any hindrance but three depots are still incomplete.
A controversy had arisen over the remaining work of Bus Rapid Transit in 2020. The JV Chinese and local contractors had refused to continue work on the BRT corridor and three mega shopping plazas (depots) worth Rs 10 billion. Construction work on all three depots had been stalled for months. The Peshawar Development Authority has decided to replace the JV contractors to complete the remaining work of the PTI flagship project. Asian Development Bank has approved the assignment agreement to hand over the remaining work to subcontractors.
According to data available with this correspondent, the BRT Reach-I, (Chamkani to Balahisar Fort) was 97.72% completed while 2.28% of work is in progress. The PDA has paid Rs 9,307,311,059.41 to the contractor and the remaining work will be completed by March 2022. A de-scoping agreement has been signed and work was awarded to the subcontractor.
Reach-II (Balahisar Fort to Aman Chowk ) 96.51 per cent of work has been completed, while only 3.49% minor work is awarded to a subcontractor to complete by March 2022. PDA has paid an amount of Rs 9,541,582,184.04 to the main contractor.
Similarly, 94.59% of the work of Reach-III (Aman Chowk to Karkhano Market) has been completed and 5.41% of work is awarded to a subcontractor and the completion date is March 2022. PDA has already paid an amount of Rs 12,740,980,829.95 to the main contractor. Three mega shopping and car plazas are also part of the BRT but the contractor had refused to complete the work on these plazas. The Hayatabad Depot, 81.33%, Chamkani 82.71, and Dabgari has76.24% per cent of work has been completed so far and 18.67%, 17.29, and 23.76% work is remaining, respectively.
-
Bruno Mars Leaves Taylor Swift Behind With Shocking Move -
Trump Administration Imposes 25% Tariff On Imports Of Some AI Chips -
Chinese Smartphone Makers Adjust Prices As Costs Go Up -
Wikipedia Owner Signs AI Content Training Deals With Microsoft, Meta -
Meghan Markle’s Real Feelings Revealed Amid UK Return Rumours -
Reese Witherspoon Issues Urgent Warning After Scammers Using Her Identity -
XAI Restricts Grok Image Editing After Backlash From California And Europe -
‘Disgraced’ Andrew’s Past Scandals Catch Up To His Daughters -
Amazon Rolls Out ‘sovereign’ EU-based Cloud To Address Data Privacy Concerns -
Ross, Matt Duffer Used AI To Write Finale Of 'Stranger Things'? -
Microsoft Secures Largest Ever Soil Carbon Credit Agreement Amid Data Centres Expansion -
Google Expands Gemini With Personal Intelligence -
Japan, Philippines Sign Defence Pacts As Regional Tensions Escalate -
ISS Crew Of Four Completes Medical Evacuation With Safe Splashdown Off California -
Connor Storrie Reveals Why His Dad Hasn't Seen 'Heated Rivalry' Yet -
Meghan Markle’s Biggest Challenge In UK Return As She Struggles To Control Narrative