CDA officials visit IJP Road, review development work
By APP
September 19, 2021
Islamabad : Members Engineering, Capital Development Authority on Saturday along with DG Works, Director Road South, Nespak Consultant and NLC team visited IJP Road area of Islamabad and took a detailed look at the pace of development work.
They issued orders for early commencement of survey, soil investigation, pile road test to the concerned staff, said a news release issued here.
The project were scheduled to be completed in 18 months with the total cost of Rs4.9 billion.
It may be recalled that under the project two bridges and two flyovers would be constructed on IJP Road to reduce traffic congestion, flyovers on 9th Avenue and IJP Road while two bridges would be constructed at Kataria and Pirwadhai to ensure smooth flow of traffic.
-
Andrew, Sarah Ferguson Refuse King Charles Request: 'Raising Eyebrows Inside Palace' -
Adam Sandler Reveals How Tom Cruise Introduced Him To Paul Thomas Anderson -
Washington Post CEO William Lewis Resigns After Sweeping Layoffs -
North Korea To Hold 9th Workers’ Party Congress In Late February -
All You Need To Know Guide To Rosacea -
Princess Diana's Brother 'handed Over' Althorp House To Marion And Her Family -
Trump Mobile T1 Phone Resurfaces With New Specs, Higher Price -
Factory Explosion In North China Leaves Eight Dead -
Blac Chyna Opens Up About Her Kids: ‘Disturb Their Inner Child' -
Winter Olympics 2026: Milan Protestors Rally Against The Games As Environmentally, Economically ‘unsustainable’ -
How Long Is The Super Bowl? Average Game Time And Halftime Show Explained -
Natasha Bure Makes Stunning Confession About Her Marriage To Bradley Steven Perry -
ChatGPT Caricature Prompts Are Going Viral. Here’s List You Must Try -
James Pearce Jr. Arrested In Florida After Alleged Domestic Dispute, Falcons Respond -
Cavaliers Vs Kings: James Harden Shines Late In Cleveland Debut Win -
2026 Winter Olympics Snowboarding: Su Yiming Wins Bronze And Completes Medal Set