close
Friday March 29, 2024

Transmission line energised

By Our Correspondent
May 24, 2020

LAHORE : National Transmission and Despatch Company (NTDC) is completing its ongoing projects on fast track with best utilization of resources despite Covid-19 pandemic, says a company spokesperson here Saturday.

In a later development in this connection, the construction of 38 kilometer long 500 kV double circuit quad bundle transmission line consists of 126 towers for Looping in and out 500 kV single circuit, Haveli Bahadur Shah-Gatti Circuit-II at 500 kV Grid Station Faisalabad West has been successfully energised on load on May 22. The NTDC spokesman has said that the transmission line is transmitting power from Haveli Bahadur Shah power plant to 500 kV grid station Gatti (Faisalabad) via under construction 500 kV Grid Station Faisalabad West. The spokesman further said that construction work at 500 kV Grid Station Faisalabad West is also being completed at fast pace. The completion of the project will yield to tackle the increasing demand of electricity of domestic, industrial, commercial and agriculture consumers. While updating about the completion of another task on war footing, the spokesman said that NTDC team has also completed the installation/erection work of a collapsed tower of 500 kV Rawat- Neelum Jhelum transmission line and the said transmission line has been energized successfully. NTDC Managing Director Engr Dr. Khawaja Riffat Hassan has appreciated the efforts of NTDC teams for completing both these tasks by working day and night during the corona virus pandemic especially in Eid holidays.