Dasu Hydropower Project makes progress
PESHAWAR: In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete-Starter Dam has been completed upstream of the main dam site.
A communication said as per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages.
The Stage 1 is up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season - a major landmark which the project team successfully achieved.
As the high flow season has started, the Indus River is flowing through the two diversion tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.
After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out.
-
Nicola Peltz Billionaire Father Speaks Out On Beckham Family Drama For First Time -
Andrew Mountbatten-Windsor's Living Situation Gets Worse Amid Epstein Controversy -
King Charles Blindsided By Andrew-Epstein Blunder -
Sharon Osbourne Reacts To Ozzy Osbourne 2026 Grammy Tribute -
Kate Middleton Breaks Silence On Newest Member Of Wales Family -
Harry Styles, Zoe Kravitz Taking Romance On Tour? -
Mark Ruffalo Responds To Firing Rumours From Marvel -
Princess Beatrice, Eugenie Will Not Be Abandoned By Royals Amid Scandal -
Sarah Ferguson Questioned ‘what Kind Of Mother Is She’ Over Epstein Scandal -
Melinda Gates Breaks Silence On Epstein Allegations Linked To Bill Gates -
Matthew McConaughey Prefers First Takes For Emotional Movie Scenes -
'The Housemaid' Director Shares Major Deleted Scene Will Appear In Sequel -
Here's How David Harbour Split Planted Lily Allen's Musical Comeback -
New York Deploys Observers To Monitor Trump's Deportation Efforts -
Drew Barrymore Shares Unfiltered Take On Dating Men In Their 20s -
9 Million Android Phones Hijacked Worldwide In Hacker Network: Google