LAHORE: National Transmission and Despatch Company (NTDC) has started construction of 75-km long 500 kV double circuit transmission line for transmission of power from 870 MW Sukki Kinari hydropower project.
The project is funded by Asian Development Bank (ADB) with estimated cost of Rs79,930 million under PSDP. The transmission line is expected to be completed by April 2023.