PDA gives deadline for completion of Peshawar BRT
PESHAWAR: Finally the Peshawar Development Authority (PDA) has set a deadline for the completion of the remaining part of Bus Rapid Transit (BRT), Peshawar. The minor work on the main corridor and finishing works of three building projects at Hayatabad, Dabgari, and Chamkani is expected to be completed by the end of June 2022.
The PDA had already paid an amount of Rs 37.687 billion to the contractor for the civil work of the main corridor and three incomplete mega plazas. However, the BRT corridor is fully operational without any hindrance but three depots are still incomplete.
A controversy had arisen over the remaining work of Bus Rapid Transit in 2020. The JV Chinese and local contractors had refused to continue work on the BRT corridor and three mega shopping plazas (depots) worth Rs 10 billion. Construction work on all three depots had been stalled for months. The Peshawar Development Authority has decided to replace the JV contractors to complete the remaining work of the PTI flagship project. Asian Development Bank has approved the assignment agreement to hand over the remaining work to subcontractors.
According to data available with this correspondent, the BRT Reach-I, (Chamkani to Balahisar Fort) was 97.72% completed while 2.28% of work is in progress. The PDA has paid Rs 9,307,311,059.41 to the contractor and the remaining work will be completed by March 2022. A de-scoping agreement has been signed and work was awarded to the subcontractor.
Reach-II (Balahisar Fort to Aman Chowk ) 96.51 per cent of work has been completed, while only 3.49% minor work is awarded to a subcontractor to complete by March 2022. PDA has paid an amount of Rs 9,541,582,184.04 to the main contractor.
Similarly, 94.59% of the work of Reach-III (Aman Chowk to Karkhano Market) has been completed and 5.41% of work is awarded to a subcontractor and the completion date is March 2022. PDA has already paid an amount of Rs 12,740,980,829.95 to the main contractor. Three mega shopping and car plazas are also part of the BRT but the contractor had refused to complete the work on these plazas. The Hayatabad Depot, 81.33%, Chamkani 82.71, and Dabgari has76.24% per cent of work has been completed so far and 18.67%, 17.29, and 23.76% work is remaining, respectively.
-
Huge Donations Made On Eric Dane GoFundMe -
Matty Healy Sets Summer Wedding Date Close To Ex Taylor Swift's Nuptials -
Jennifer Lawrence On Her Complicated Relationship With Fame While Battling Rejection: 'Annoying' -
Protest Held Outside Andrew Mountbatten-Windsor Home -
NASA Targets March 6 For Launch Of Crewed Mission Around Moon Following Successful Rocket Fueling Test -
Conan O'Brien Addresses Rob Reiner's Tragic Death After Explosive Clash At Christmas Bash -
Princess Eugenie, Beatrice's Major Plan With King Charles Revealed After Andrew Arrest -
Prince William Out Of Trouble As King Charles Faces Andrew Scandal Fallout -
Sir Paul McCartney Gets Honest About Whether He Broke Up The Beatles -
Brad Falchuk, Gwyneth Paltrow's Husband, Opens Up About Eric Dane's 'Famous Last Words' -
Sarah Ferguson Leaves Andrew 'furious' With Stunning Move: 'It's All-out War Now' -
Greenland Ice Sheet Acts Like ‘churning Molten Rock,’ Scientists Find -
Sydney Sweeney Pays Tribute To 'Euphoria' Co-star Eric Dane After His Death: 'Forever Will Love You' -
Kayla Nicole Reveals Surprising Reason Behind Separation From Travis Kelce -
Andrew Made Major Demand To King Charles Before Arrest -
Political Tensions Steal Spotlight At Berlin Film Festival Closing Ceremony