PDA gives deadline for completion of Peshawar BRT
PESHAWAR: Finally the Peshawar Development Authority (PDA) has set a deadline for the completion of the remaining part of Bus Rapid Transit (BRT), Peshawar. The minor work on the main corridor and finishing works of three building projects at Hayatabad, Dabgari, and Chamkani is expected to be completed by the end of June 2022.
The PDA had already paid an amount of Rs 37.687 billion to the contractor for the civil work of the main corridor and three incomplete mega plazas. However, the BRT corridor is fully operational without any hindrance but three depots are still incomplete.
A controversy had arisen over the remaining work of Bus Rapid Transit in 2020. The JV Chinese and local contractors had refused to continue work on the BRT corridor and three mega shopping plazas (depots) worth Rs 10 billion. Construction work on all three depots had been stalled for months. The Peshawar Development Authority has decided to replace the JV contractors to complete the remaining work of the PTI flagship project. Asian Development Bank has approved the assignment agreement to hand over the remaining work to subcontractors.
According to data available with this correspondent, the BRT Reach-I, (Chamkani to Balahisar Fort) was 97.72% completed while 2.28% of work is in progress. The PDA has paid Rs 9,307,311,059.41 to the contractor and the remaining work will be completed by March 2022. A de-scoping agreement has been signed and work was awarded to the subcontractor.
Reach-II (Balahisar Fort to Aman Chowk ) 96.51 per cent of work has been completed, while only 3.49% minor work is awarded to a subcontractor to complete by March 2022. PDA has paid an amount of Rs 9,541,582,184.04 to the main contractor.
Similarly, 94.59% of the work of Reach-III (Aman Chowk to Karkhano Market) has been completed and 5.41% of work is awarded to a subcontractor and the completion date is March 2022. PDA has already paid an amount of Rs 12,740,980,829.95 to the main contractor. Three mega shopping and car plazas are also part of the BRT but the contractor had refused to complete the work on these plazas. The Hayatabad Depot, 81.33%, Chamkani 82.71, and Dabgari has76.24% per cent of work has been completed so far and 18.67%, 17.29, and 23.76% work is remaining, respectively.
-
Inside Meghan Markle’s Plans ‘With Love, Meghan’: Season 3 And Valentines Day Specials -
King Charles Gets Caught Between A Rock And A Hard Place For The Second Time With Harry -
Dolly Parton Hints At More Music As She Marks 80 -
Simu Liu Reveals How His Family Treated Him After He Started Acting -
Gwyneth Paltrow Mourns Valentino As She Calls His Death 'end Of An Era' -
Three-year-old Allegedly Tortured, Killed During Exorcism In California Church -
Blake Lively Gushes She And Ryan Reynolds Are 'partners In Everything' -
Teyana Taylor Reflects On Co-parenting Journey With Ex Iman Shumpert -
Blake Shelton Recalls Being 'nervous Wreck' On Adam Sandler Film -
Prince Harry's Lawyer Tells Court Daily Mail Complicit In Unlawful Acts -
Meghan Markle Named In Epstein Files With Ghislaine Maxwell? -
Drunk Driver Tries To Snatch San Diego Deputy’s Gun During Chase -
After Surgery, Piers Morgan Reminded Of His Remarks About Meghan's Father's Hospitalization -
Idris Elba Gets Honest About Managing Real-life Hijack Situation -
Royal Family Buries King Charles' Cousin -
Elizabeth Hurley Faces An Impossible Choice As Son Damian, Beau Billy Ray Cyrus Clash