Pesco starts rehabilitation in Chitral
ISLAMABAD: Rehabilitation of electricity installations started by Pesco on the direction of Ministry of Water and Power is progressing fast in the flood affected areas of Chitral and electricity lines on more than 600 poles checked and rehabilitated so far. The supply to Darosh Grid Station (which covers one third
By our correspondents
July 23, 2015
ISLAMABAD: Rehabilitation of electricity installations started by Pesco on the direction of Ministry of Water and Power is progressing fast in the flood affected areas of Chitral and electricity lines on more than 600 poles checked and rehabilitated so far. The supply to Darosh Grid Station (which covers one third of Chitral) restored temporarily on emergent basis.
In the restored areas, the Pesco management has been asked to observe zero loadshedding to facilitate rescue and relief operations.However, material on 35 locations of Jutilasht Line is being shifted but the process is facing difficulties due to washed away roads and bridges.General Manager GSO of PESCO Niaz Muhammad along with his team directed to camp in the district Chitral to restore supplies as soon as possible.
District Chitral is fed by two 33KV Grids, Darosh Grid and Jutilasht (Main Chitral) Grid with 967 poles. Both were affected by floods. The areas affected are those fed from Jutilasht grid including Chitral city, Jutilasht, Chumar Kund, Orghuch, Baghrabad, Joghor, Dinin etc. Some 6,000 connections are affected. However these will be fed from Chitral Hydel (1MW) on one hour loadshedding after 4 hour basis in different areas. Close coordination is established between Ministry of Water and Power and provincial governments.
In the restored areas, the Pesco management has been asked to observe zero loadshedding to facilitate rescue and relief operations.However, material on 35 locations of Jutilasht Line is being shifted but the process is facing difficulties due to washed away roads and bridges.General Manager GSO of PESCO Niaz Muhammad along with his team directed to camp in the district Chitral to restore supplies as soon as possible.
District Chitral is fed by two 33KV Grids, Darosh Grid and Jutilasht (Main Chitral) Grid with 967 poles. Both were affected by floods. The areas affected are those fed from Jutilasht grid including Chitral city, Jutilasht, Chumar Kund, Orghuch, Baghrabad, Joghor, Dinin etc. Some 6,000 connections are affected. However these will be fed from Chitral Hydel (1MW) on one hour loadshedding after 4 hour basis in different areas. Close coordination is established between Ministry of Water and Power and provincial governments.
-
Huge Donations Made On Eric Dane GoFundMe -
Matty Healy Sets Summer Wedding Date Close To Ex Taylor Swift's Nuptials -
Jennifer Lawrence On Her Complicated Relationship With Fame While Battling Rejection: 'Annoying' -
Protest Held Outside Andrew Mountbatten-Windsor Home -
NASA Targets March 6 For Launch Of Crewed Mission Around Moon Following Successful Rocket Fueling Test -
Conan O'Brien Addresses Rob Reiner's Tragic Death After Explosive Clash At Christmas Bash -
Princess Eugenie, Beatrice's Major Plan With King Charles Revealed After Andrew Arrest -
Prince William Out Of Trouble As King Charles Faces Andrew Scandal Fallout -
Sir Paul McCartney Gets Honest About Whether He Broke Up The Beatles -
Brad Falchuk, Gwyneth Paltrow's Husband, Opens Up About Eric Dane's 'Famous Last Words' -
Sarah Ferguson Leaves Andrew 'furious' With Stunning Move: 'It's All-out War Now' -
Greenland Ice Sheet Acts Like ‘churning Molten Rock,’ Scientists Find -
Sydney Sweeney Pays Tribute To 'Euphoria' Co-star Eric Dane After His Death: 'Forever Will Love You' -
Kayla Nicole Reveals Surprising Reason Behind Separation From Travis Kelce -
Andrew Made Major Demand To King Charles Before Arrest -
Political Tensions Steal Spotlight At Berlin Film Festival Closing Ceremony