Neelum-Jhelum project to take months to be fully operational

By Khalid Mustafa
May 21, 2018

ISLAMABAD: In a shocking development, the Rs503 billion Neelum-Jhelum Hydropower Project will not be able to run on its full capacity to generate 969 MW in coming three to four months as unit-4 of 242 MW has virtually been dismantled to pull out the rotor that was badly damaged.

Advertisement

This unit was first made operational at the time of project’s inauguration on April 13 by Prime Minister Shahid Khaqan Abbasi and since then, it has been non-functional. The unit was first made operational in violation of SoPs in a haste which is why its rotor was badly damaged, a top official privy to the development told The News.

Now, the top management of the project say Unit-4 will take 3-4 months to come on stream meaning by that the project will not be fully functional in this summer season, as after four months, the winter season would set in and the water flows will be reduced by that time which is why the hydro generation of 969 MW will not be achieved till next summer season, the officials argued.

The sources at the site of the project said that John Gummer, world known personality who had already extended his services in Tarbela power plants, lost his temper when he was called on the site of the unit-4.

He concluded that SOPs for running the unit were not adhered to as at the outset, hydropower unit is run after every15 minutes pause and after certain time the unit is made operational gradually.

Senior official while quoting John Gummer said that SOPs were violated while running the unit-4 by the top management of Neelum-Jhelum Hydropower Company Limited as it was in a haste and wanted to make it operational at inauguration time.

Now the Chinese experts’ team has arrived from Herbin city of China. Herbin city is known for manufacturing the hydropower plants and other heavy machinery. However, later on, Wapda spokesman issued a press release mentioning that unit-4 will take 3-4 months to come on stream. Right now, the official said, the project is injecting in the system 242 MW for the last two days by running the unit-1.